National Standard Interpretation

GB/T 48023-2026 "Technical Specifications for Cold Plate Liquid Cooling System of Data Center" Standard Interpretation

GB/T 48023-2026 is China's first national-level unified standard for cold plate liquid cooling systems, covering the full lifecycle of data center cold plate liquid cooling systems from design, manufacturing, deployment to operations. The standard was issued on July 30, 2026 and officially implemented on February 1, 2027.

Standard TypeRecommended National Standard (GB/T)
Issue Date2026-07-30
Effective Date2027-02-01
Administered bySAC/TC 28
Content Map

Quick Navigation

This page systematically outlines the framework and core content of the GB/T 48023-2026 standard for quick reference.

Key Metrics Quick Reference

10%

Flow uniformity: max/min branch flow difference ≤ arithmetic mean 10%

95%

Heat transfer capacity: actual ≥ 95% of design load at rated conditions

2027-02-01

Standard official effective date

85%+

Cold plate share of liquid cooling market

Standard Overview

1.1

Basic Information

ItemContent
Standard No.GB/T 48023-2026
Chinese Name数据中心冷板式液冷系统技术规范
English NameTechnical specifications for cold plate liquid cooling system of data center
Standard TypeRecommended National Standard (GB/T)
Issue DateJuly 30, 2026
Effective DateFebruary 1, 2027
Pages24 pages
Word Count35 thousand characters
Issued byState Administration for Market Regulation, Standardization Administration of China
Administered byNational Information Technology Standardization Technical Committee (SAC/TC 28)
Lead DrafterDawning Data Infrastructure Innovation Technology (Beijing) Co., Ltd.
1.2

Standard Positioning

GB/T 48023-2026 is China's first national-level unified standard for cold plate liquid cooling systems, covering the full lifecycle of data center cold plate liquid cooling systems from design, manufacturing, deployment to operations. The issuance of this standard marks the formal transition of cold plate liquid cooling technology from "sporadic pilots" to "large-scale deployment," ending the industry's long-standing lack of unified guidelines and product incompatibility.

1.3

Standard Structure

ChapterTitle
1Scope
2Normative References
3Terms and Definitions
4Abbreviations
5System Composition
6Technical Requirements
7Test Methods
Appendix A (Normative)Secondary side coolant indicator requirements and test methods
Appendix B (Normative)Secondary side system installation, pressure holding, and flushing

Background and History

2.1

Industry Pain Points

Pain PointSpecific ManifestationImpact
Lack of Unified Technical StandardsCold plate dimensions, quick connect fitting specs, and CDU interface standards vary by manufacturerManufacturer A's cold plate cannot adapt to Manufacturer B's manifold; poor system compatibility
High Customization CostsNearly every project requires a new round of customization adaptationDesign costs and delivery cycles remain high
Unclear Responsibility BoundariesData center construction parties, cooling suppliers, and整机 manufacturers have unclear responsibility divisionsMutual blame when faults occur
Lack of Standards for Safe OperationsLeakage monitoring, corrosion prevention, and coolant selection have no unified requirementsMarket has widespread concerns about liquid cooling safety
No Threshold for Long-term ReliabilityLack of unified testing and verification systemProduct quality is uneven
2.2

Drivers

AI Computing Explosion (Demand Side)

Single chip power consumption from 200W→700W→1000W+; air cooling hits physical ceiling; single cabinet power density from 80kW→200kW→1MW+

PUE Policy Constraints (Policy Side)

New data center PUE requirements ≤1.25 in most regions, core areas ≤1.15; air cooling PUE typically 1.8, cooling electricity consumption accounts for 40%+ of total power

Large-scale Deployment (Market Side)

158 intelligent computing bids above 100 million RMB in first 7 months of 2026; winning amounts exceed 113 billion RMB; customization costs become a "tax" on the industry chain

2.3

Standard Type Explanation

GB/T 48023-2026 is a Recommended National Standard (GB/T), not a mandatory standard (GB). However, in practical applications, large intelligent computing centers and operator procurement typically write national standards into technical bid requirements, making them contract-level hard thresholds once referenced.

Scope and Timeline

3.1

Scope

DimensionContent
Applicable ScenariosDesign, manufacturing, deployment, and operations of data center cold plate liquid cooling systems
Not ApplicablePhase-change cold plate liquid cooling systems (two-phase cold plate is not within scope)
Applicable ObjectsLiquid cooling product and service providers, application units, and computing facility users
3.2

Implementation Timeline

TimelineEvent
July 30, 2026Standard officially issued (Standardization Administration Announcement No. 33, 2026)
August 2026 ~ January 2027Transition preparation period (~6 months)
February 1, 2027Standard officially implemented

System Architecture and Terminology

4.1

Core Terminology

TermEnglishDefinition
Cold Platecold plateA cavity with internal fluid channels that utilizes coolant circulation within these channels to achieve heat dissipation
CoolantcoolantThe medium that absorbs and transmits heat in a liquid cooling system
Cold Plate Liquid Cooling Systemcold plate liquid cooling systemA system that transfers heat from IT equipment components to enclosed circulating coolant through cold plates, exchanges heat through one or more cooling circuits, and ultimately dissipates heat to the outdoors
Secondary Side Cooling Systemsecondary side cooling systemA cooling system that absorbs heat from IT equipment components through enclosed coolant circulation and exchanges heat with the primary side cooling system
Primary Side Cooling Systemprimary side cooling systemA cooling system that dissipates heat from the secondary side cooling system to the outdoor atmospheric environment or through a heat recovery system
4.2

System Composition

The standard clearly defines two core parts of the cold plate liquid cooling system:

Secondary Side Cooling System (Inside Cabinet)

  • Cold plate assembly
  • Quick Connect (QC)
  • Manifold
  • Secondary side piping
  • CDU (Coolant Distribution Unit)

Primary Side Cooling System (Outside Cabinet)

  • Primary side piping
  • Cooling source (cooling tower/dry cooler)

CDU Core Role

CDU is the hub for heat exchange between primary and secondary sides, providing secondary side flow distribution, pressure control, physical isolation, and anti-condensation functions.

4.3

Abbreviations

AbbreviationFull NameChinese Meaning
CDUCoolant Distribution Unit冷量分配单元
ITInformation Technology信息技术
PUEPower Usage Effectiveness电能利用效率
TIMThermal Interface Material导热界面材料

Technical Requirements

5.1

Three-Dimensional Technical System Architecture

General Requirements

  • Material compatibility
  • Appearance and marking
  • Corrosion prevention
  • Safety protection
  • Electrical safety

Component-specific Requirements

  • Cold plate assembly
  • Quick connect fittings
  • Manifold
  • CDU performance
  • Piping requirements
  • Leakage monitoring

System Performance Indicators

  • Flow uniformity ≤10%
  • Heat transfer capacity ≥95%
  • Pressure loss
  • Temperature uniformity
  • Long-term operational stability
5.2

Quantitative Performance Indicators

Indicator CategorySpecific IndicatorQuantitative Requirement
Flow UniformitySecondary side piping branch flow deviationDifference between max and min ≤ 10% of arithmetic mean of all branch flows
Heat Transfer CapacityActual system heat transfer at rated conditionsShall be no less than 95% of design load
Pressure LossSystem piping resistanceShall comply with design requirements
Temperature UniformitySecondary side supply/return water temperatureShall comply with design requirements
5.3

Six Core Specification Modules

Specification ModuleCore RequirementsPain Point Solved
Cold Plate AssemblyUnified indicators for materials, dimensions, thermal performance, and reliabilityEach manufacturer's cold plates are incompatible
Quick Connect DevicesInterface dimensions, sealing performance, and insertion/removal life standardizationFittings not universal, leakage risk
CDUHeat exchange performance, control precision, and safety protection requirementsLack of unified basis for cabinet-to-cabinet heat exchange
Hydraulic Calculation ModelUnified calculation methods for piping resistance and flow distributionEach manufacturer's design parameters are not comparable
Testing and Verification MethodsStandard procedures for performance testing and reliability testingNo basis for acceptance
Deployment and OperationsInstallation specifications, operation monitoring, and maintenance cycle requirementsLack of operations standards

Testing Methods

6.1

Testing Coverage

Testing LevelTest ItemCorresponding Standard Chapter
Component-levelCold plate thermal performance testingChapter 7
Component-levelQuick connect sealing testingChapter 7
Component-levelCDU performance testingChapter 7
System-levelFlow uniformity testingChapter 7
System-levelHeat transfer capacity testingChapter 7
System-levelPressure loss testingChapter 7
Safety-levelLeakage detection testingChapter 7
6.2

CDU Core Acceptance Indicators

Inspection ItemAcceptance Standard
Flow testingWithin design flow ±5%
Temperature control accuracySecondary side supply water temperature stable at set value ±0.5°C
Leakage detectionSimulate leakage; trigger alarm and auto-shutdown within 2s
Redundant switchingBackup pump input within 5s
Noise≤75 dB(A) at 1m from CDU
CommunicationNormal communication with BMS; data refresh cycle ≤5s

Secondary Side Coolant Specifications (Appendix A)

7.1

Coolant Classification and Selection Trends

Coolant TypeMain ComponentsAdvantagesApplicable Scenarios
PG 2525% propylene glycol + 75% deionized waterEasy maintenance, extremely low toxicity, anti-freezeLarge data centers, long-link systems (mainstream trend)
EG 2525% ethylene glycol + 75% deionized waterLower cost, anti-freezeCost-sensitive projects
Deionized WaterPure waterOptimal thermal conductivity, low costShort-link, small-scale systems, indoor constant temperature environments
7.2

Coolant Key Indicators

Physicochemical Performance Indicators

  • Freezing point
  • Boiling point
  • pH value
  • Conductivity

Performance Indicators

  • Corrosion inhibition performance
  • Thermal stability
  • Oxidation resistance

Installation, Pressure Holding, and Flushing (Appendix B)

8.1

Engineering Key Points

ProcessCore Requirements
InstallationPiping laying, fitting connections, and bracket fixation shall comply with design documents and construction specifications
Pressure HoldingPressure holding test shall be conducted after system installation to verify sealing and detect leakage in piping and fittings
FlushingPiping flushing shall be conducted before system operation to remove construction residues and ensure coolant circulation system cleanliness
AcceptanceData center infrastructure overall construction and acceptance shall comply with standard requirements

Referenced Standards

9.1

Normative References

Standard No.Standard NameReference Role
GB/T 8446.2Heat sinks for power semiconductor devices Part 2: Thermal resistance and flow resistance measurement methodsCold plate thermal performance test method reference
GB 50242Code for acceptance of construction quality of building water supply and drainage and heating engineeringPiping installation and pressure holding test acceptance
GB 50243Code for acceptance of construction quality of ventilation and air conditioning engineeringCooling system construction acceptance
GB 50462Standard for construction and acceptance of data center infrastructureData center overall construction and acceptance framework
GB 50738Code for construction of ventilation and air conditioning engineeringCooling system construction process specification
9.2

Related Standards Updates

Standard No./Plan No.NameStatus
T/CECS 1722-2024Liquid cooling data center technical requirementsIssued
T/TAF 324-2026Cold plate liquid cooling cabinet system technical requirements and test methodsIssued
20263064-Z-469General design guide for immersion liquid cooling power modules for data centersBeing drafted

Industry Impact and Market Prospects

10.1

Market Size and Penetration

Indicator20252026 (E)2027 (E)
Global AI chip liquid cooling penetration33%53%~60%
China liquid cooling server penetration20%37%>50%
Cold plate share of liquid cooling market85%+80%-85%75%-80%
China liquid cooling data center market size—232.5 billion RMB—
10.2

Core Industry Chain Value Distribution

SegmentValue ShareCore Companies
Cold Plate Assembly35%-40%Envicool (domestic market share >30%), AVIC Jicheng, Feirongda
CDU25%-30%Shenling Environment (domestic market share #1), Vertiv, Envicool
Quick Connect Fittings5%-10%AVIC Jicheng (UQD included in NVIDIA MGX ecosystem)
Coolant~10%Various specialized formulation manufacturers
Piping System5%-10%Wanda Technology, Yizhou Data

Common Misconceptions and Clarifications

Misconception 1: GB/T 48023 is a Mandatory Standard

Clarification: The "T" in GB/T stands for "Recommended" and is not itself a mandatory standard. However, in practical projects, large intelligent computing centers and operator procurement typically write national standards into technical bid requirements, making them contract-level hard thresholds once referenced.

Misconception 2: The National Standard Covers All Liquid Cooling Technology Routes

Clarification: The national standard focuses on cold plate liquid cooling systems and explicitly does not apply to phase-change cold plate liquid cooling systems (two-phase cold plate). Immersion liquid cooling standardization work is being advanced separately.

Misconception 3: All Data Centers Must Switch to Liquid Cooling After Standard Implementation

Clarification: The standard applies to new design, manufacturing, and deployment; it does not apply retroactively to completed projects. Liquid cooling initial investment is 30%-50% higher than air cooling, but 5-year TCO is 18%-25% lower than air cooling.

Misconception 4: The Standard is Dominated by a Single Company

Clarification: The standard is administered by the National Information Technology Standardization Committee, organized by the China Electronics Standardization Institute, with participating units covering multiple segments of the industry chain (led by Dawning Data Infrastructure, jointly with Huawei, Alibaba Cloud, Vertiv, Schneider Electric, and dozens of other industry-university-research-user units).

Misconception 5: Cold Plate Liquid Cooling Simply Means Placing a Cold Plate Directly on a Chip

Clarification: Cold plate liquid cooling system is a complete engineering system including quick connect fittings, manifolds, piping systems, CDU, coolant, monitoring systems, safety protection, and other full-chain components.

Standard Limitations

Does Not Cover Phase-Change Cold Plate Liquid Cooling

Two-phase cold plates use coolant phase change for more efficient heat transfer (heat dissipation capacity up to 385W/cm²), but standardization is low, limiting short-term adoption.

Coolant Formulation Standards Still Imperfect

PG 25, EG 25, and deionized water have not yet achieved complete unification. Each manufacturer's functional additive formulations are core technical secrets and not disclosed externally.

Recommended Standard Enforcement Depends on Market Transmission

The actual enforcement effectiveness depends on downstream bid inviters' references, third-party testing institutions' capability building, and industry chain parties' self-discipline levels.

Frequently Asked Questions (FAQ)

Q1

What scenarios does GB/T 48023-2026 apply to?

A: Applicable to the full lifecycle of design, manufacturing, deployment, and operations of data center cold plate liquid cooling systems. Not applicable to phase-change cold plate liquid cooling systems (two-phase cold plate).

Q2

When will the standard be officially implemented? How long is the transition period?

A: The standard was issued on July 30, 2026 and officially implemented on February 1, 2027, with a transition period of approximately 6 months. Teams planning or bidding intelligent computing projects before the standard implementation date should prepare technical specifications according to national standard requirements.

Q3

Is GB/T 48023 a mandatory or recommended standard?

A: A Recommended National Standard (GB/T). "T" stands for "Recommended." Non-compliance does not result in administrative penalties, but large intelligent computing projects and operator procurement typically write national standards into technical bid requirements, making them contract-level hard thresholds once referenced.

Q4

What are the two most important quantitative indicators in the standard?

A: Flow uniformity: the difference between maximum and minimum branch flow rates in the secondary side piping shall not exceed 10% of the arithmetic mean of all branch flow rates. Heat transfer capacity: under rated conditions, the actual system heat transfer capacity shall be no less than 95% of the design load.

Q5

Why did the standard choose cold plate liquid cooling over immersion cooling?

A: Cold plate liquid cooling accounts for over 85% of the current liquid cooling market, with the highest technology maturity, lowest retrofit difficulty, and most complete industry ecosystem. NVIDIA GB200/GB300/Vera Rubin platforms all adopt cold plate solutions.

Q6

What is CDU's role in the system?

A: CDU is the hub for heat exchange between primary and secondary sides, providing secondary side flow distribution, pressure control, physical isolation, and anti-condensation functions. The standard formally incorporates CDU functional positioning into the specifications.

Q7

Are Appendix A and Appendix B informative or mandatory?

A: Both Appendix A and Appendix B are Normative Appendices with equal binding force as the main technical requirement text and are mandatory provisions.

Q8

What specific requirements does the standard have for coolant?

A: Appendix A specifies coolant physicochemical performance indicators (freezing point, boiling point, pH value, conductivity, etc.) and performance indicators (corrosion inhibition, thermal stability, etc.) along with corresponding test methods. Currently, the industry is trending toward PG 25 (25% propylene glycol + 75% deionized water).

References

No.SourceLink
1China Standards Online Servicehttps://www.spc.org.cn/...
2China Electronics Standardization Institutehttps://www.cesi.cn/...
3Standard Full Text (book118)Standard Original PDF
4Yang Xin Ming Xue (TouTiao)Standard Core Content Interpretation
5Cold Plate Liquid Cooling National Standard is Here (TouTiao)Six Major Specification Modules Analysis

Disclaimer: This article interprets GB/T 48023-2026 based on public sources for reference only. The specific technical requirements of the standard shall prevail based on the official published version of the national standard.